Venetia Valley School
-
Thank you for visiting this page which features updates on construction at Venetia Valley School.
Click to view finishes for TK classrooms
Click to view plan for the middle school quad
Restroom Building Project
The restroom building, adjacent to the Middle School at Venetia Valley K-8, is in a deteriorated condition. Additionally,a drainage swale is needed to re-direct water away from the school property line and into an existing storm drain. These projects were identified as part of the Bond Measure A program.
BACKGROUND:
The existing restroom building adjacent to the middle school will be demolished and replaced with a new restroom building with eight (8) single occupancy student toilet rooms and one (1) staff toilet room. This project will include an accessible pathway from the middle school campus and a new concrete drainage swale designed to redirect water away from the school property line.
BEAM Construction Enterprises, Inc. was the lowest responsive and responsible bidder. This work will begin in October and be completed in March, 2024.
Reports & Meeting Notes
-
3/8/24 VV Restroom Building Progress Report
3824 Update Venetia Valley Restroom Building Project.pdf 549.86 KB (Last Modified Yesterday at 12:28 PM) -
3/15/24 VV Restroom Building Progress Report
31524 Update Venetia Valley Restroom Building Project.pdf 573.83 KB (Last Modified Yesterday at 12:26 PM) -
2/16/24 VV Restroom Building Progress Report
21624 Update Venetia Valley Restroom Building Project.pdf 578.91 KB (Last Modified on February 26, 2024) -
2/9/24 VV Restroom Building Progress Report
2924 Update Venetia Valley Restroom Building Project.pdf 470.6 KB (Last Modified on February 26, 2024) -
2/2/24 VV Restroom Building Progress Report
2224 Update Venetia Valley Restroom Building Project.pdf 571.83 KB (Last Modified on February 2, 2024) -
1/26/24 VV Restroom Building Progress Report
12624 Update Venetia Valley Restroom Building Project.pdf 478.96 KB (Last Modified on January 29, 2024) -
1/19/24 VV Restroom Building Progress Report
11924 Update Venetia Valley Restroom Building Project.pdf 468.95 KB (Last Modified on January 29, 2024) -
1/12/24 VV Restroom Building Progress Report
11224 Update Venetia Valley Restroom Building Project.pdf 569.64 KB (Last Modified on January 16, 2024) -
1/5/24 VV Restroom Building Progress Report
1524 Update Venetia Valley Restroom Building Project.pdf 571.46 KB (Last Modified on January 5, 2024) -
12/29/23 VV Restroom Building Progress Report
122923 Update Venetia Valley Restroom Building Project.pdf 554.57 KB (Last Modified on January 3, 2024) -
12/22/23 VV Restroom Building Progress Report
122223 Update Venetia Valley Restroom Building Project.pdf 646.02 KB (Last Modified on January 3, 2024) -
12/15/23 VV Restroom Building Progress Report
121523 Update Venetia Valley Restroom Building Project.pdf 512.85 KB (Last Modified on January 3, 2024) -
12/8/23 VV Restroom Building Progress Report
12823 Update Venetia Valley Restroom Building Project.pdf 583.23 KB (Last Modified on January 3, 2024) -
12/1/23 VV Restroom Building Progress Report
12123 Update Venetia Valley Restroom Building Project.pdf 382.97 KB (Last Modified on December 4, 2023) -
11/24/23 VV Restroom Building Progress Report
112423 Update Venetia Valley Restroom Building Project.pdf 374.91 KB (Last Modified on December 6, 2023) -
11/17/23 VV Restroom Building Progress Report
111723 Update Venetia Valley Restroom Building Project.pdf 270.69 KB (Last Modified on December 6, 2023) -
11/10/23 VV Restroom Building Progress Report
111023 Update Venetia Valley Restroom Building Project.pdf 311.24 KB (Last Modified on November 13, 2023) -
11/3/23 VV Restroom Building Progress Report
11323 Update Venetia Valley Restroom Building Project.pdf 300.67 KB (Last Modified on November 7, 2023)
Site Facilities Committee
-
Critical to the success of the site work is collaboration with the school communities. Venetia Valley has a Site Facilities Committee that is currently meeting to lead in the project design, details and planning for implementation for the school's bond program work.
The Site Facilities Committee is made up of teachers, staff, parents and community members. They are joined by the project team, including architects, engineers, project and/or construction managers and school and District staff, in guiding the design and planning work at the school.